In this episode of the Connectology® podcast, Connectologists® Pete Aston, Catherine Cleary, and Nikki Pillinger unpack the latest developments in grid connections, Gate 2 timelines, and ongoing industry reforms. With some DNOs now issuing grid variation offers with just 10–14 days to accept, developers are facing serious time pressure—especially when terms are unclear or revised.
The team explores when and how it may be possible to push for more time and why being prepared matters more than ever.
They also run through key Gate 2 milestones:
• Application window: 8–29 July
• NESO decisions expected in September
• Offers issued from October (for transmission) and from January (for distribution) Submitting early is strongly recommended—leaving it late could mean delays, basic application rejections, or missing the window altogether. But getting an offer is only half the battle.
The team digs into whether these Gate 2 offers will actually be deliverable, given the rising costs and complexity developers are facing.
Major challenges include:
• High SGT reinforcement costs
• Large security and liability obligations
• Risky curtailment terms
• More demanding application and deposit requirements
With submissions due by 29 July and NESO support limited from 6 August, time is running short.
Recorded 24 June 2025
Our links: Website: https://roadnighttaylor.co.uk/
Newsletter sign up: https://roadnighttaylor.co.uk/connect...
Follow us on LinkedIn: / roadnight-taylor-ltd
Find if we fit at info@roadnighttaylor.co.uk
No comments yet. Be the first to say something!