Connectologists® Catherine, Philip and Alex ask whether standardising substation design means we're now building too much grid.
Key themes discussed include:
- the cost of going big: a substation built to serve multiple future customers can cost £100m–£150m and use up to 100 acres of land - several times the £20m–£30m it costs to build a smaller substation for a single customer
- a live example: one project was moved to a new, larger substation meant to serve several customers - but most of those other customers dropped out after Connections Reform, leaving a big substation to be built for demand that no longer exists
- a question of intent: is building big and scaling back later a deliberate strategy, or just a lack of one
- the planning horizon: there's no Strategic Spatial Energy Plan yet to guide where new substations should go, and around fourteen years of demand is already queued up - so how far ahead should operators be planning
- a risk to innovation: always reaching for a big new substation could mean that smarter options, like sharing existing bays, get overlooked
Recorded: 09 June 2026
This content was recorded on an earlier date. The connections landscape changes rapidly, so please treat any facts, figures, and guidance as a point-in-time view and verify current information before relying on it.
Our links:
Website: https://roadnighttaylor.co.uk/
Newsletter sign up: https://roadnighttaylor.co.uk/newsletter/
Follow us on LinkedIn: https://www.linkedin.com/company/roadnight-taylor-ltd/
Find if we fit at info@roadnighttaylor.co.uk
Version: 20241125
No comments yet. Be the first to say something!